|
CSAA Livermore

Figure
1: California State Automobile Association Inter-Insurance Bureau (CSAA-IIB)
Member Service Center (CSAA is an affiliate of AAA) |
Building
Design Features
Underfloor
Air Distribution System Characteristics
UFAD
System Performance
|
|
Building
Use:
Serves as the Northern California call center for CSAA.
Currently houses 300 of the 400 total possible occupants.
Location: Livermore, California
Design Team:
| Owner/developer: |
CSAA-IIB |
| Architect: |
Levoski/Donaldson |
| Mechanical
Design: |
ACCO
Mechanical |
| Contractors: |
Harbison Mahoney Higgins, Inc.
|
|
Size:
Two-story (equal floor area per floor)
7,407 m2 (80,000 ft2)
Construction
Status:
Completed in 1997
|
Building Design Features
The
construction of this building is typical for the rapidly growing area of
Livermore. A combination of tilt-up concrete walls with generous windows is
used. Some areas of the exterior wall are windowless, as shown in Figure 1, but
about 60% of the exterior wall area is glazed. For windowed areas the glazing
accounts for about 75% of the wall surface. These windows are double-glazed,
slightly gray tinted with an estimated shading coefficient of 0.6. Manually
operated perforated metal interior blinds (blinds blades are non-perforated on
West exposure) are provided for all windows. An overhang shades the lower story
windows.

Figure 2:
Interior Layout
Inside,
virtually the entire building is open plan with only a few private offices on
the perimeter. Conference rooms and services are concentrated in the central
area of each floor, as are the mechanical services and roof-mounted equipment.
Modular
furniture by Steelcase is used throughout. Some interior areas are provided
with 1.5 m (5 ft) high partitions; other areas have minimal partitions as shown
in Figure 2. Raised floors cover virtually the entire building except in the
entry lobby. Glued down non-coincident carpet tiles, 0.46 m x 0.46 (18 x 18
in), are used for the surface treatment. Swirl diffusers are used throughout
the building for both perimeter and interior areas. They are generously
supplied and located close to workstations in many instances, as shown in
Figure 2. A suspended acoustical ceiling includes ceiling mounted fluorescent
lighting fixtures.
Electrical
distribution is accomplished as follows: Hard conduit is used from the central
core to various distribution junction boxes (J-box); flexible conduit is used
between the junction box and a similar one screwed to the floor panels in a
workstation. Another flexible conduit is used to connect the workstation J-box
to a furniture based electrical distribution system. Telecom cables are free
run in the plenum and then pass through small holes drilled through the floor
panels
Top
Underfloor Air Distribution (UFAD) System Characteristics
Design Intent
CSAA desired a state-of-the-art solution and a high efficiency building. The high
concentration of computers used to support the call center work also motivated
an access floor for power and communications cabling flexibility. CSAA
had experience with at least two other projects before this one, and based on
the positive results from those, decided to use a UFAD system for this project.
Design/Configuration
| Plenum
Height: |
0.61
m (24 in) |
| Diffuser
Types: |
Swirl
diffusers, supplied by Titus are used throughout the building. |
| Raised
Floor: |
0.61
m (24 x 24 in) concrete-core panels using a post and stringer mounting
system supplied by Tate. |
|
Supply
Air Temperature:
|
Nominal
17°C (63°F), varies with load. |
| UFAD
System Types: |
Titus
single duct VAV boxes supply variable volume, constant temperature (VAV-CT)
air to perimeter and interior. Hot water reheat is used in the perimeter
for heating. |

This
system, as depicted in Figure 3, exemplifies one system type commonly used in
early UFAD installations. It is essentially a VAV overhead system installed in
the underfloor plenum space. Underfloor ducting supplies VAV boxes that deliver
air into partitioned underfloor perimeter and core zones. Perimeter partitions
are 9.14 m (30 ft) from the exterior walls. Zone sizes vary from about 83 m2
(900 ft2) in perimeter corner offices to about 417 m2
(4500 ft2) in the interior. One or two VAV boxes typically serve a
zone. Service areas in the central core are treated in a similar manner. Each
zone contains swirl diffusers that are uniformly laid out; a row of diffusers
is located along the exterior walls as shown in Figure 4.

Figure
4:
Perimeter Diffuser Layout
|
Operation
The
operation of this system is relatively simple. Pneumatic
thermostats control the VAV boxes. Cooling
is controlled by varying the volume of ~17°C (65°F) air to each
partitioned plenum zone via one or two VAV boxes; air is in turn supplied
to the space though the floor diffusers. In the larger zones where two VAV boxes are used, a single
thermostat controls both. Heating
is provided to perimeter zones by activating a hot water reheat coil when
the zone is calling for heating (and airflow is minimum). Additional
sensors that connect to the Johnson (JCI) Metasys building management
system have been installed at various interior locations. These are used primarily for monitoring purposes and to indicate
when the supply air temperature should be reset in response to the
occupied space being too hot or cool. Otherwise
the JCI system controls only the central equipment and system scheduling. Scheduling is generally not required since this building is a 24/7
operation. Air is returned to
the AHUs through ceiling light fixtures and return grilles via a ceiling
plenum. Some areas such as the lobby and restrooms use a conventional
overhead system.
|
UFAD
System Performance
The
complaint rate has dramatically dropped after an initial shake out period (see
CBE Findings). In general the system meets the objectives of CSAA and
provides good overall comfort. The
easy and quick relocation of the diffusers to accommodate individual needs and
easy access to services infrastructures in the plenum were noted as a
significant benefit.
CBE
Findings
(These
comments reflect the views of CBE researchers based on a limited study of the
building and do not necessarily represent those of the designers and/or owners)
Overcooling
- The system was initially operated with 12.7°C (55°F) supply air, which
resulted in numerous “too cool” complaints. Once the supply setpoint was adjusted to its current range of 17°C (65°F),
the complaints ceased.
Too
cool complaints were exacerbated by the fact that a number of diffusers were
located too close to the occupants. The
occupants also had difficulty with adjusting the diffuser dampers. Some of these dampers became stuck, frustrating the occupant’s
attempts to lower the airflow. In
addition, occupants sometimes replaced the diffuser plate upside down,
causing further problems. Before these problems were addressed by relocating
diffusers occupants would turn the offending diffusers off by placing paper
inside or a phone book on top.
During
a recent carpet renovation project (see below) it was discovered that as
many as 50% of the diffusers were closed off. For this type of system
closing a large number of diffusers exacerbates overcooling at the remaining
open ones; although the supply fan speed is controlled to maintain duct
pressure, plenum pressure is not controlled thus resulting in increased
plenum pressure as diffusers are closed down. This
has resulted from many diffusers being inappropriately placed relative to
occupants; relocation of the diffusers became a central activity during the
renovation; diffuser relocation should be a recognized and planned part of
any renovation project.
Nighttime
cool complaints continue and most likely are a result of the inability to
increase zone temperature setpoints for nighttime operation. This
results from using pneumatic thermostats and may be exacerbated by the
minimum stops for the VAV boxes being set too high. Although
more expensive, a direct digital control (DDC) system extended to the VAV
boxes would allow more flexibility to control these zones. Using large perimeter zones so that the perimeter skin loads
are not separately controlled from the interior loads may also exacerbate
this condition.

Figure 5: Broken Diffuser
Diffuser
- Not long after occupancy mechanical problems with the diffusers began to
appear. Some diffusers broke at
the floor flange as shown in Figure 5. The locking ring sometimes fell off so
that the diffuser was loose in the floor. Also some occupants would remove the
basket damper because it became stuck. Without the basket the diffuser plate
position was slightly lower than the ring presenting a problem for chair
rollers and potentially a tripping hazard. Titus has improved and replaced all
defective flanges. The maintenance staff monitors the diffuser adjustment
activities of occupants to ensure that adjustments are being made properly.
Carpet
tiles - Carpet problems have resulted from the original installation of a
newly offered cushion-backed carpet tile. Apparently
the combination of an unsheathed cushion backing material and overly
aggressive glue resulted in de-lamination when carpets were pulled up. The
carpet supplier is replacing the tiles with new 50 cm x 50 cm (19.6 in x 19.6
in) standard, non-cushioned carpet tiles.
Floor
panels -The floor panels are not screwed
down. This would appear to
compromise the integrity of the floor system but does make changing the panels
a little easier. However, the
raised floor installation uses a stringer system, which is common in computer
room applications. Typically, the
panels with corner screws were designed for use without stringers in office
applications (i.e., post support system). Structural integrity is provided by diagonal seismic bracing at regular
intervals that was engineered for the local seismic zone.
Perimeter
offices - Some offices have no independent control since they are built-up
from lightweight partitions after occupancy and therefore are subject to the
control of the zone in which they are located. This did not appear to be a significant problem. The original design included some perimeter offices that are provided
with dedicated VAV boxes.
Furniture
layout – The modular furniture was laid out on a diagonal for aesthetic
reasons. However, this diagonal layout does not correlate well with the
diffuser layout, which was done with a standard rectangular grid. This
points to the need for coordination between the design and installation of the
furniture and floor systems.
Maintenance
– Some large particle debris resides in the diffuser baskets. This
apparently is not a problem and the facility manager sees no reason to clean
them out regularly, thus helping to keep maintenance costs low (or at least
does not add to maintenance cost).
Renovation
– The facility manager reports that contractors find working with the raised
floor system very easy, which helps to lower renovation costs. In this regard the 0.61 m (2 ft) high plenum is a distinct advantage
– the electrical contractors can work in the underfloor plenum during normal
working hours, thereby reducing overtime costs associated with having to take
up floor panels in workstations during off hours. Also, drilling access holes in floor panels can be accomplished without
special tools.
Date
Reviewed: June 2000
Print-friendly version
|